Is there a limit when exporting tasks into Excel .csv file? Example: truncate at 2000 rows, etc

Trevor Overstreet April 20, 2022

I need to know if there is a row limit when exporting issues into a csv file. Please and thank you!

1 answer

1 accepted

1 vote
Answer accepted
Fabio Racobaldo _Herzum_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 20, 2022

Hi @Trevor Overstreet ,

welcome to the Atlassian community!

Yes, there's a limit for export and it is 1000 rows. Please take a look to the following article https://confluence.atlassian.com/jirakb/increase-issue-limit-for-excel-exports-in-jira-cloud-779160811.html

Hope this helps,

Fabio

Trevor Overstreet April 20, 2022

Thank you for the quick response! How about the Jira integration into excel? I'm seeing 50k rows. Is this accurate?

The workaround should work but curious about the below. 

 

Screen Shot 2022-04-20 at 11.50.13 AM.png