You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hi,
I created a bamboo plan and I had Stage1 and Stage2 under that.
FYI.. Stage1 has its own tasks in correct order and Stage 2 has its own tasks.
When I trigger the build, Stage2 is getting started immediately. Not sure why this is happening? Is there any possibility to fix this?
Moreover this is not happening all the times, During my nightly build it works perfect. When I trigger manually, Stage2 is getting started sometimes.
Request for an early help.
Hi!
looks like you setup multiple one
https://confluence.atlassian.com/bamboo/using-stages-in-a-plan-289276862.html
Shortly, you can workaround it by final stage :)
Cheers,
Gonchik Tsymzhitov