My Bamboo Plan Stage2 runs before Stage1 when I trigger the build, how to change that?

vishnuvardhan vangala
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 8, 2019

Hi,

I created a bamboo plan and I had Stage1 and Stage2 under that.

FYI.. Stage1 has its own tasks in correct order and Stage 2 has its own tasks. 

When I trigger the build, Stage2 is getting started immediately. Not sure why this is happening? Is there any possibility to fix this? 

Moreover this is not happening all the times, During my nightly build it works perfect. When I trigger manually, Stage2 is getting started sometimes.

Request for an early help.

1 answer

0 votes
Gonchik Tsymzhitov
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 9, 2019

Hi! 

looks like you setup  multiple one

https://confluence.atlassian.com/bamboo/using-stages-in-a-plan-289276862.html

 

Shortly, you can workaround it by final stage :)

Cheers,

Gonchik Tsymzhitov