Has anyone worked out a way to run the next stage in a plan if a job in a previous stage failed in bamboo specs?
I've looked at making the next stage final but I would like the plan to stop first and then have the ability to move on.
Hello Orla,
Welcome to Atlassian community !
Stages are meant to run only if the previous stage was successful.
If you do need to run a stage whatever the outcome of the other stages is you need to use a final stage. This has been described on Using stages in a plan too.
You can also look for manual stage - A user has to trigger this type of stage manually to run it.