Jira Structure Gantt view to show Estimated vs logged effort

JK August 28, 2024

Hi Team, Is there a way in Jira Structure Gantt + resource view, to show how much a task was estimated and how much effort actually logged by assignee.

Example:

Current Date: 30Aug2024, UserStory_001 - Estimated 5 days, with start date as 1-Sep-2024

Current Date: 03Sep2024, UserStory_001 - User logged total 3 days effort (1 day effort daily from 1sep to 3rd sep, so total logged effort shown in jira is 3 days)

In this case, is there a possibility to show in Gantt view , how much effort was logged against the estimated period

Also in Resource usage view, can we get view of how much effort was planned on particular day for a resource and how much effort was logged by them

1 answer

Suggest an answer

Log in or Sign up to answer
1 vote
Stepan Kholodov _Tempo_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 1, 2024

Hello @JK 

I answered a similar question in this post of yours: https://community.atlassian.com/t5/App-Central-questions/Jira-Structure-gantt-resource-usage-to-show-logged-efforts-for/qaq-p/2797895#U2827221
This might help.

Best regards,
Stepan
Tempo (the Structure app vendor)