Hi Guys,
I have an Automation that When a Date of an Issue Change, automatically change other 2 date with same Date. I need to upgrade another Field(Date type) with the date augmented of 7 Days, I have tried the comand .plus(7) but it doesen't Work. There is a way to do that?
I'm using Jira cloud and I have the Premium
I put the Screenshot of the Automation with the component when I need to increase the date
Thanks
Hi @erika_zanoni ,
please try this:
{{issue.customfield_10036.plusDays(7)}}
See here for documentation.