When using Rapid Board, how do I ensure each team member has enough work?

jiminoc
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 26, 2012

While doing planning sessions using Rapid Board what are some reasonable ways to make sure each person on the team has a decent enough amount of work for the length of the sprint?

e.g. if you have 10 people on the team, how can you quickly see if 1 person only has 2 hours worth of work? Are you supposed to wait for them to speak up or can this be done through Greenhopper somehow?

thanks

1 answer

Suggest an answer

Log in or Sign up to answer
1 vote
Danielle Zhu
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 30, 2012

Not with existing GreenHopper Rapid Board reports. A workaround may be add your time estimate column to the Issue Navigator, and query issues with Sprint in openSprints() and sort by assignee.