Hi All, I am using roadmaps to plan capacity of my teams to help me to figure out if the workload can be increased or not.
I am creating a capacity overview per assignee/sprint/project using the filters on the roadmap page, e.g. it gives me 8.1 scrum points for "christian", now looking at the corresponding sprint in the jira backlog/active sprint, it shows 13 points.
The sources of the roadmap board has been set correctly to include the project that is shown in jira. I checked all setting more than twice but I can't find the problem.
What is going wrong here?