Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

What sets the "Scheduled start" date?

David Doria February 9, 2018

In the Scope panel, issues have a column called "Scheduled start". Unlike "Target start" and "Target end", this does not seem to be editable. Presumably this date is getting pulled from some information on the actual issue - is there a way to change this date?

3 answers

1 vote
Surbhi Soni May 26, 2023

Hi @David Doria , Its probably late and already have answer to it but still want to share my findings.

  • The "Scheduled Start" & "Scheduled End" date picks up data from the "Target Start" & "Target End" dates respectively.
  • "Target Start" & "Target End" are Locked Date field specifically created for Portfolio in JIRA.

image.png

  • One way is you add both of the fields in the JIRA tickets screens and then update the dates.

OR

  • In Plan, you can choose any other custom date field suitable to display the start and end date in configuration Setting of Plan.
  • So by this you are basically telling Plan to consider the custom date field.
  • Make sure the custom dates you select here is present in all issue screen & is populated.

image.png

Note: I tested this in JIRA DC version 8.20.

0 votes
Florian Friedebold
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 12, 2018

Have you tried editing the start date of your first or concerned 'Version' resp. 'Release' ?That's accessible via your board, where you can also see your epics.

If you have the dependencies set up properly between your epics and tasks, the 'Scheduled Start' should recalculate to a new date.

Best regards

David Doria February 9, 2018

So is the answer "no"? There seem to be some things, like the list of sprints that this issue has been in, that are part of the "history" and cannot be changed - is this correct? Thew view for "Scheduled range: Full" is goofy because of this, where something extends back many months just because it has been pushed to future sprints a few times.

Thomas
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 14, 2018

The scheduled start and end columns you are mentioning are not part of a Jira issue data and represent the scheduling calculation result. It is not possible to change those currently.

 

More generally the values given by the calculation are not modifiable as they represent the idealistic dates decided by Portfolio for the data currently in your plan. 

Hillary Moore December 29, 2023

Which date fields are used by the scheduling calculation? Which dates fields have to be populated in order to calculate a schedule?

Like Eric Bailey likes this

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events