I am trying to create a plan in JIRA cloud.
I have added the estimates(d) column to the plan. The columns picks up the remaining estimate column value.
The column gets populated only when there is not sub task in the story. when there is a sub task and when the include subtask check box is clicked in the story , the value does not show up in the plan .
Can someone help me with the this issue
Hello @Selva Praveen Elango ,
Welcome to the community!
Advanced Roadmaps will show either a "Story points" field or an "Estimates (h/d)" field. "Story points" maps directly to the "Story points" field on the issue once changes are committed via the Review changes dialog. "Estimates (h/d)" actually maps to "Time remaining" which can be found in the "Time tracking" section on the Jira issue.
Could you please validate whether these fields are part of subtask issue type.