1. I plan sprint in jira: all stories are estimated, one team member is assigned to a single story. In portolio (capacity view) i see 100% capacity utilization, so my plan is ok.
2. Now sprint is activated, team members start working on issues. One story is completed and marked as done.
3. When i move to portfolio assignee is ok, but now in the capacity view i see that my capacity utilization is 96% and i have resources that are underplaned.
In my opinion - the situation should not affect the free capacity when sprint is active until i dont change estimates or replan the sprint.
I think that something is wrong or my configuration is bad. What am i missing?
Scheduling options
Assignee import level: Sub-task
Maximum assignees per story: not set
All other options: on