Hello,
We update recently to 3.0 Portfolio version and we are having some issues regarding the absences days of teams members and the impact on teams capacity.
Use case:
Team is created in Managed share teams and their sprint velocity is 40 story points.
This teams has 5 members and 2 of them in be in Annual Leave the entire next sprint. AN is configured in team Member Absences Days in Team Management window.
When go back to plan, we're finding theses issues:
1 - The sprint capacity doesn't update according to team absences. So, we have 40 story points of capacity in all sprints and future sprints.
2 - Portfolio is not distributing capacity over future sprints. The next sprint is 213% full based on estimations and the following sprints are 0% even though there will be tasks that will last for future sprints.
3 - The Auto-Schedule is calculating unrealistic dates, target ends such as Saturdays and Sundays.