Jira Plans: Dragging and dropping issues between Releases

Zach Siegel​
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 1, 2024

I'm experiencing an issue within Jira Plans where I am attempting to drag and drop issues from one Release to another in the List view.

I have sorted by Rank, as I know that is the only way to enable drag and drop, but the issue persists. Any thoughts?

Screenshot of my View Settings below: 

Jira plans view settings issue.png

1 answer

0 votes
Bryce Lord
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 1, 2024

Hi @Zach Siegel​ ,

Unfortunately, I don't believe there is a way to change the Release by dragging and dropping work items from one Release to another.

The typical way to move work items from one Release to another in the plan is to add the "Releases" field to the fields shown and make the necessary changes within that field.

Hope that helps.

 