Hi everyone, I am using Jira advanced roadmaps and created "plans" including initiatives and epics. So far so good.
Next step was to add a "program", so that I can aggregate different plans. In the configuration of the "program" I added my plans.
Problem: when I select "hierarchy level = epic" on the program dashboard, everything works as expected (diagram shows epics with some bars on timeline). But not, if I select "hierarchy level = initiatives". Nothing is shown ("for this hierarchy no initiatives are planned"), even though I created some initiatives for my plans/program (with start/end dates). I also synchronized / refreshed plans/programs.
Thanks for any tips / advice
found it out myself - after another "synchronize" on the "tab = scope" my initiatives are now shown on the dashboard für "program".