Running into a limitation where our estimates are in hours and the timeline view is limited to days. As a result, some of the tasks that are less than 24 hours are rounded up to 1 day. This affects our ability to schedule and resource effectively for projects.
I've tried going to program/plans settings but haven't been able to find solution. How can I achieve more granularity in the timeline view, i.e., in hours and not days.