I m trying to create a plan in Portfolio to monitor the capacity of the team members across all our projects.
We are using SCRUM and the story points assignment is at the story / defect level. The SP estimate combines both DEV and QA Effort. Therefore, this doesn't reflect well in the capacity view in Portfolio.
I tried to create DEV and QA sub-tasks and assign the SPs at that level. This gave me more accuracy in the capacity view. However, when i submit the changes to JIRA, the SP assignment at the sub-task level overrides the total SP at the story level. In this case, the Agile board is no longer reflecting the SP as needed.
How can i resolve this? is there a way to get an accurate capacity view in Portfolio yet keep the SP assignment at the story level?
Hope that someone has the answer!
Thanks,
J