I have been trying to capacity plan in the new Advanced Roadmaps that replaced Portfolio for Jira and so far I have only been able to get the points vs velocity to show in a 'current sprint' in the roadmap but not in the 'projected sprint'. Any thoughts as to why that might be happening or what I can do different?
Thanks.
Hi Jason,
The estimates allocation vs velocity info is only available for active or future sprints. You can create future sprints in your Jira board and estimate/velocity information would become available in the plan.
Nonetheless, that is a good feature suggestion. I would encourage you to create a suggestion ticket here so other users could comment and vote for it.
I hope that helps, happy to hear your thoughts.