Portfolio excludes issues which are marked as 'done' in capacity view

1. I plan sprint in jira: all stories are estimated, one team member is assigned to a single story. In portolio (capacity view) i see 100% capacity utilization, so my plan is ok.

2. Now sprint is activated, team members start working on issues. One story is completed and marked as done.

3. When i move to portfolio assignee is ok, but now in the capacity view i see that my capacity utilization is 96% and i have resources that are underplaned.

In my opinion - the situation should not affect the free capacity when sprint is active until i dont change estimates or replan the sprint.

I think that something is wrong or my configuration is bad. What am i missing?

Scheduling options

Assignee import level: Sub-task

Maximum assignees per story: not set

All other options: on

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,645 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you