JIRA portfolio - stories are taken in concurrent Edited

After creating the plan, different stories and epics taken concurrently. I want that to be changed in a way once story A is complete Story b can be taken.

Example: 

Story A (100 story points) and Story B (100 story points)

Team velocity: 100

portfolio schedule showed like : Sprint 1 - Story A and B (each 50 points burned)

Sprint 2: both stories are done.

 

Expected: Sprint 1: Story A complete and Sprint 2: Story B complete

 

Can you please help on how to change the settings to incorporate this?

1 answer

0 votes

Hello Mohamed,

It sounds like Story B has been manually added to the same sprint that Story A is part of.  And when Manual association is in place this overrides the calculation performed by portfolio.

Check out the Scheduling Behavior Documentation for more details on this.

-Earl

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Confluence

👁‍🗨 Confluence Team planning dashboard_Atlympics 🌈

Hi Atlassian's, How is your journey with #Atlympics 2021 so far....excited! Me too, same excitement. Here's my typical team planning and vision dashboard which I used to share to my management and ...

59 views 1 4
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you