Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,559,414
Community Members
 
Community Events
184
Community Groups

Time Tracking in Greenhopper

I am estimating in story points and time tracking in hours. I want the remaining hours field in the user story to be the total of the remaining hours in the sub-tasks. But I cannot enter sub-task remaining hours in Plan mode, only in Work mode. The user story is not available in Work mode until I start the sprint. But if I start the sprint without remaining hours in the user stories, the ideal burn-down chart is not plotted.

It's a Catch-22 situation. The only way I can get the initial burn-down plotted is to put guesswork hours remaining nto the user stories, whereas they should be the sum of the sub-task hours remaining. But I can't enter the sub-tasks hours remaining until I've started the sprint.

Surely I should be able to enter sub-task hours remaining in Plan mode?

Jira 5.2.5 Greenhopper 6.1.2

2 answers

1 accepted

1 vote
Answer accepted
Dobroslawa Wierzbicka
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Mar 21, 2013

You cannot edit the Sub-tasks' remaining estimates directly in the Plan mode, but you should be able to edit the field in the Sub-task's Edit Screen (click Actions > Edit in the Sub-tasks section of the Story's detail pane). Would that be a suitable workaround for you?

I can't speak for the original poster, but given the workflow we're talking about, it's an inefficient workaround at best.

My team have basically 2 hours for our Sprint Planning meeting every two weeks and we have to get through a lot of stories... selecting which stories to include, then breaking down with sub-tasks how we'll approach each one. With an average of 30-35 stories, half of which need to be broken down into 2-5 sub-tasks each, I figure there are ~50 or so times we need to enter a sub-task remaining estimate during the 60-75 minutes we have left after agreeing on the sprint contents.

You can see how the inefficiency can multiply quickly when its core to the workflow...

Maybe there's just a better way to organize our workflow that aligns with the software design?

I asked the very same question on the Configurating Estimation and Tracking page and would love to hear an answer on this!