When we set up a due date in the issue itself, the due date on the backlog dashboard shows 1 day earlier than the actual due date.
Hello @Nicolas Sannier,
Thank you for reaching out to Atlassian Community!
Testing on my local site, I was able to replicate the same issue.
I can see that you have only Jira Core on your site, so the issue is happening on a Business project.
This issue was reported as a bug and our dev team is already working on a fix:
Please, click on “This affects my team” and also watch to receive updates about the fix.
Kind regards,Angélica
Hi Nicolas - can you share some screen shots of both?
Hi John, please see attached. The ticket due date is October 28 but dashboard shows October 27.
Very strange - I would put in a support ticket with Atlassian:
https://support.atlassian.com/contact/#/
It is on the free cloud service so I cannot submit any tickets, I can only use the community page.
Okay - let me see if I can get someone from Atlassian to take a look at it.
Thanks Angélica!!
Thank you both!