I have many projects in Jira and I want that no one is able to add any issue in the backlog to my current or future sprint without my permission.Is it possible to do that?
Hi @Sushant Verma ,
For issue creation in Backlog the following permission is needed. --> Create issue
To add issues into Sprint (Current / Future) --> Schedule issue
Thanks
Welcome to the community , can you please confirm the project types either its classic or NextGen.
For classic projects, you can edit the permissions scheme and remove permission for Schedule issues.
Reference
https://support.atlassian.com/jira-cloud-administration/docs/permissions-for-classic-projects/
Hello @KAGITHALA BABU ANVESH Thanks for your reply! I want that no one is able to add the issues to my sprints. Do I need to change the Schedule issue permission scheme or any other way to do that?Thanks!
@Muhammad Ramzan_Atlassian Certified Master_ Thank you!It's Classic or NextGen both!
Hi ,
Yes you can remove others from "Schedule issues" permission.
I have added only the Group "administrator" to the Schedule issue.Is it fine?
This one is only for classic projects. If someone does not have schedule issues permissions they cannot add any issue to the sprint.
@Muhammad Ramzan_Atlassian Certified Master_ What about NextGen projects?
For Next gen projects , its "Edit any due date" but for nextgen you need to perform the same action on all projects one by one as they don't share the permissions.
To be honest, I did not personally try this permission , either it works for the sprints or not, but as per the official documentation, its mentioned that its same as schedule issue in classic projects
Please give a try and share your experience.
https://support.atlassian.com/jira-software-cloud/docs/next-gen-permissions/