Hi Community!
I need a little help with some questions about using Jira Software burn down charts and tracking time. I'm very new on Jira Software, so, please be as much specific as you can!
1) I would like to know why my burn down charts looks like it looks in the the attached image. We are estimating issues using time (hours) instead of story points at the subtasks level. The story is not being estimated neither time recorded.
https://drive.google.com/file/d/1IJetrbsGev6QUtvNxrKWBBknUJJwxAaR/view?usp=sharing
Is there any idea of what I'm doing wrong based on the attached chart result?
2) How can I obtain a report or dashboard to get estimated time vs remaining time by assignee, task, etc?
Thank you!