How to add time estimate, time logging, time tracking fields currently present in task into EPIC?
1. JIRA Settings > Issues > Issue Features > Time Tracking
Enable Time Tracking and modify the time tracking settings as applicable.
2. JIRA Settings > Issues > Fields > Field Configurations
On the Field Configuration settings, choose the applicable Field Configuration. You will find the field name 'Time Tracking'. Add the screen names that is relevant to the issue type EPIC.
This way time tracking can be enabled.
@Divya Suseelan Thank you for your reply. I could not find time estimate field.
@Ankit Goyal Are you using Next Generation Project? If yes, Time tracking isn’t there yet but is planned.