Hi
We have just started our sprint, and I am surprised to notice that the timetracking shows 189 our of 194 hrs as in progress, as that is not the case.
The stories, except for 4, are all in the to-do stage and "grey" - meaning not in progress.
I double checked the workflow as well, and all looks ok.