Hello
I'd like to create a filter that will identify when more time is spent on a task than the original estimate.
So far I got to the below query :
project = MSA AND fixVersion = "Sprint 7" AND status = "In Progress" AND issuetype = "Technical task" AND ( (remainingEstimate + timeSpent) > originalEstimate )
Once the filter has been setup notifactions will be sent out to the relevant people.
Please help !
Thank you
Sannette