As screenshot below, I have my data format mapping with mask but when I do the validate, JIRA told me that it's wrong
2016-09-14 14_35_19-External System Import - FI2.0.png2016-09-14 14_32_49-External System Import - FI2.0.png
2016-09-14 14_32_51-E__1_working_BPO_task_BPO_Task_import.tsv - Notepad++.png
It's always got error with TODAY() but if I set due date from tomorrow to future, error gone
but in my project, i have a lot of task create at the morning and due on today() need imported
You might check the similar issue: https://community.atlassian.com/t5/Jira-questions/dates-on-csv-import/qaq-p/251637
When importing, and your Jira format is: dd/MMM/yy h:mm a
from an excel csv file, use custom format: dd/mmm/yy h:mm AM/PM
Right click and select cell formatting. Click on Custom. Select any date configuration, then manually enter in the custom format above into 'Type'. You should be able to import fine afterwards.