Hi,
I'm facing a problem with the Burndown chart.
I've planned my Sprint 3, and after adding ALL the Stories I start it on the 30/08.
The problem is that the burndown chart is showing the stories as if they were added after the sprint start, as Scope change. Even more akward is that it is marking this Scope changes as one per day for future dates always at 6:00.
Attached is the current Burndown chart on the 02/09.
Any idea what is the cause of this behaviour? And own can I solve it?