Hello,
I am having a very difficult time adjusting the rank. Also, from the portfolio plan, when I change rank, I need to commit the changes. When I try to commit the changes, I am getting following error.
image2016-8-29 11:10:23.png image2016-8-29 11:10:44.png
What could be the possible reason. Need help ASAP.
Regards,
Ashwin
Have you opened a support ticket? Can you rank issues in that project normally? What details are hidden under Show Details.
I'm also having this problem. Details are:
I was getting the same error and figured out that I did not have the permission.
For the solution: Go to "Permission Scheme" of the project and be sure that you have permission for "Schedule Issues".