Hello, lately JIRA is driving me crazy; we created one extra step, namely "Live" which is an ending step. The transition from Done to Live has a post function: The Resolution of the issue will be set to Done. That marks the issue as done and when closing sprint everything is fine. The problem arises when we have some tasks as Done, these issues are not marked as done they are somehow incomplete even if it is written "Resolution:Done" thus resulting to move issues in backlog when closing sprints. How this can be fixed? The transition from previous step has also a similar post function. Same behaviour is noticed when the transition from previous step has resolution screen (any resolution->same).