How to remove field 'Remaining estimate' from JIRA
The field that enables:
is Time Tracking.
You can choose whether or not to show the three of them, with no more granularity than that.
You can hide Time Tracking by any of these methods:
Thanks for your quick answer.
I appreciate that.
Can you please provide the navigation for reaching Time Tracking
Sure:
Cog Icon > Issues > Time Tracking
time-tracking.png
That is what the remaining sum is telling you.
Can the unused fields be removed with scriptrunner? they are causing confusion.
They're not fields, it's all one field. So, no, you can't get a handle on the bits of the field.
Thanks for the reply even if it is bad news.