I have a scrum board using JIRA Agile Cloud.
It's using Agile Simplified Workflow. However I've added some more columns to also include tracking on which enviroment issues are deployed
image2015-4-9 16:18:8.png
New columns are 'Development Complete', 'Deployed Integration', 'Deployed Acceptance'.
I also configured statusses related to these columns where the 3 columns I added have a "Category" done.
Furthermore I set resolution to done as from the 'development Complete phase'
In my Sprint Report I would like to have my issues in the completed issues list as soon as they have a status of 'Development Complete'. Accordingly I would like to see my sprint burndown decreasing. This is currenly not the case.
any idea's on how to achieve this ?