We are currently switching to the new live portfolio plan, and are quiet pleased with it over all.
However, we're having an issue with the automatic story scheduling. The issue we're having is that stories that are currently planned in our active sprint and badly incorporated in the project scope and timeline. Instead of appearing at the very stop of the story list in the scope view, they seem to be placed randomly. This completely messes up our estimate release dates, as the plan places tasks that will be completed this week to many weeks ahead.
Is this a known issue, or are we missing something?
Thanks,
Alex