Hi Community,
I'm currently testing Jira Automation in a Jira Cloud Premium Sandbox environment and would appreciate any insights regarding automation rate limits.
■Environment
- Jira Cloud Premium
- Sandbox environment
- Automation rules for automatic subtask creation
■Configuration
There are four different work item types, and each work item type has its own Automation rule.
Each rule is triggered when a parent issue transitions to a specific status and then automatically creates a subtask.
■Test Scenario
I created approximately 400 parent issues and performed the status transition.
For each parent issue, the corresponding Automation rule creates a subtask based on the applicable work item type.
■Observed Behavior
Subtask creation works correctly up to around 250 parent issues.
After that point, the Automation audit log starts showing the following error:
"This step has exceeded rate limits."
Once this occurs, subsequent subtasks are no longer created.
Initially, the audit log displayed the rate limit error above. However, subsequent audit log entries only show "Multiple errors" without providing detailed information about the underlying component failures.
The issue is not limited to a single Automation rule. The same behavior occurs across multiple work item-type Automation rules.
■Additional Information
- Jira Cloud Premium subscription
- Monthly Automation execution limit: 200,000
- Current usage is less than 1%
- The audit log indicates a rate limit error rather than a monthly execution limit issue
- Testing is being performed in a Sandbox environment
- The first rate limit errors started appearing around the 248th issue
■Questions
- Does Jira Cloud Automation have any rate limits related to large numbers of executions within a short period of time?
- Are there any Sandbox-specific limitations or differences compared to Production?
- Has anyone experienced similar behavior when bulk-generating large numbers of issues or subtasks using Automation?
- Are there recommended workarounds, such as batch processing, delays, scheduled execution, or any other best practices?
- Is it expected behavior that, after the initial rate limit error, the audit log only shows "Multiple errors" without more detailed information?
Any insights or experiences would be greatly appreciated.