We are running a company-managed software project (Jira Premium, with Advanced Roadmaps / Plans enabled).
Problem:
When we create a subtask from a parent work item, the Team field appears in the "Add subtask" form as required (marked with *) but is empty and cannot be edited/selected — the field is greyed out with a message indicating that the team cannot be changed for subtasks. When we click Create, we get the validation error:
Field "Team" is required.
This makes it impossible to create subtasks at all through the inline "Add subtask" action.
What we expected:
Based on Atlassian documentation, the subtask should inherit the Team value from its parent work item automatically. For existing subtasks, this does appear to work — for example, subtask CO-7047 has Team = "Telematics", inherited from its parent CO-5316 (also "Telematics"). However, for newly created subtasks, the Team field is empty at creation time and the required validation blocks creation.
What we have already checked/tried on our side:
- The Field Configuration does NOT list Team as required (only Issue Type, Reporter, and Summary are required there). The mandatory behavior on Team is enforced by Jira itself.
- There are no workflow validators and no automation rules that make Team required.
- We created a dedicated subtask screen without the Team field and mapped it to the Sub-task issue type. The form then opened without the Team field, but clicking Create still returned "Field Team is required." So removing Team from the screen does not bypass the backend validation. (We have since reverted this change.)
- We tried building an automation rule ("copy Team from parent to subtask"), but automation runs after the work item is created, while the "Team is required" validation blocks before creation — so it does not help for manual subtask creation.
- In global Fields, the Team field is shown as Locked with the note: "This field was created by Jira or a plugin, and can't be edited." There is no option to set a default value, configure inheritance, or change its required behavior.
- The global Create button does not offer "Sub-task" as an issue type, and its Parent field only accepts Epics — so subtasks can only be created via the inline "Add subtask" action, which is exactly where the Team validation blocks us.
Our questions/request:
- Why is the Team value not inherited/pre-filled in the "Add subtask" form at creation time, even though it works for existing subtasks and inheritance is expected?
- How can we make the parent's Team automatically populate the subtask's Team field at the moment the creation window opens, so that Team is not empty and the required validation passes?
- If this is a known limitation or bug, is there a supported workaround or configuration for a company-managed Premium project with Plans enabled?