Title: Best Jira Dashboard Gadget to Show Sprint Progress (Committed vs Completed) Instead of Created vs Resolved?
Question:
Hi everyone,
I'm trying to build a Jira dashboard for leadership and would appreciate some guidance.
We have two types of work:
Operational work – tickets are created and resolved during the sprint, so the Created vs Resolved gadget works well.
Project work – most stories/tasks are created before the sprint starts and some carry over from previous sprint and are added to the sprint during planning. During the sprint, they simply move through statuses until they are completed.
For project work, the Created vs Resolved gadget is misleading because it only counts issues created during the sprint. It doesn't reflect the total work committed to the sprint or how much has been completed.
For example:
Sprint starts with 50 issues.
Only 2 new issues are created during the sprint.
20 issues are completed.
The Created vs Resolved chart shows 2 created vs 20 resolved, but what leadership really wants to understand is:
How much work was committed at the beginning of the sprint.
How much has been completed over time.
How much work remains.
(Optionally) if additional scope was added during the sprint.
Constraints:
We need this as a Jira Dashboard gadget (to embed in a Confluence page).
We cannot use the Sprint Burndown/Burnup reports because they are board reports and aren't available as dashboard gadgets in our environment.
We'd prefer a trend/graph rather than tables or filter results.
Question: What is the best Jira dashboard gadget (or Marketplace app) to visualize sprint progress for committed work under these constraints? Has anyone implemented something similar?
Thanks in advance!