Hi there community ✌🏼
we have a printing data production team. They get their daily jobs as Jira issues. When they finished their job (issue) they put in in a "Review" state, where the job is getting reviewed by a project manager. The project manager then decides whether a correction of the data is needed. If so, he pushes the issue back to status "In Progress".
Currently, the value of remaining time estimate stays the same and is shown in the transition screen. The project manager should really adjust the remaining time estimate now, but often forgets to do so.

>> Now we're coming to the core question:
Is it possible to force a user to change / update the remaining time estimate field on transition?
One idea we came up was to create a separate custom field (e.g. "New time") on the transition screen to fetch the new user input. In a post function the value of the "new time" field will overwrite the "remaining estimate time" field.
Any more elegant ideas?
Thanks for your help!