We recently updated our project workflow by simplifying and modifying the existing statuses. After publishing the updated workflow, we noticed unexpected behavior across the board.
A large set of tickets were automatically transitioned to different statuses. More importantly, tickets that were previously part of closed sprints now show the Sprint field as “None.” We are no longer able to see those tickets associated with their original sprints in the backlog or in reports.
These tickets were already part of completed sprints, and the sprint association now appears to have been removed following the workflow update.
We would like to understand:
Why the sprint field was cleared after the workflow change.
Whether it is possible to restore the original sprint associations.
If there is any safe recovery or rollback option available.
This has impacted our sprint reporting and historical data, so your guidance on the appropriate recovery steps would be greatly appreciated.
Please let us know if any additional details are required from our end.