Is there a way to add a ticket to a sprint that is already completed?
Hello @Jean Nguyen
You need to reopen the sprint to add an issue to it.
Why are you needing to add an item to a completed sprint? If the item was worked on during the sprint why wasn't it added to the sprint while the sprint was active?
Good day! Welcome to Atlassian Community!
The Sprint field only displays Active Sprint & Future Sprints in the dropdown. To add an issue to already closed Sprint, you can either reopen the Sprint and add the issues or perform a Bulk edit operation to update the Change Sprint field with the Sprint ID of the closed Sprint. However, both actions will impact the Sprint reporting.
I hope that helps!
Thanks