We don't use story points, so our burnup chart uses item count, and in this sprint, the horizontal axis had repeated dates - I'd never seen it like that before.
Can anyone help?
Hi @Rafaela Orlando
Here are some scenarios that could cause repeated dates:
What are you sprint dates? I'm assuming that you have a very compressed sprint? Maybe a few days? I've seen this behavior when I do like a 3-5 day sprint. Try expanding your sprint dates to a full 2 weeks or maybe 7+ days? That should fix it.
yes, was a very short sprint to synchronize with the company dates.Only 7 days.Thanks for help
Thanks for help