I have created a test case and added it to a test cycle. After executing the test cycle, suppose there is a maintenance change where I modify existing steps or add new steps to the same test case.
In the Test Cycle → Test Execution section, I can see an “Update Test Script” option for that test case, which updates the execution steps manually.
I want to know if there is a way to configure this behavior to happen automatically whenever test case steps are modified.
Ideally:
The update of test execution steps should happen automatically when the test case is updated.
This behavior should be configurable, so that if needed, I can still choose to update the test script manually using the existing option.
Is there any configuration, setting, or best practice available to achieve this?