In the fix version, we have epics
If the epic's Due date has been updated -> need to change it in the fix version
If the Start date has been updated -> need to change it in the fix version
Yeah, that makes sense. I’d suggest keeping a quick checklist: whenever an epic’s Due date or Start date changes, immediately update the fix version field too. That way nothing gets out of sync and your tracking stays accurate. Maybe even set a reminder or automation if your system supports it
Welcome @julia.s
You can create two automation rules for this:
Oh sorry, forgot to add - to create an automation rule
If we update the due date of the version -> automatically update it in the epic that is marked with the same version
thx will try