Currently, I have a Jira space with a workflow as shown in the attached image. Tasks are created and managed through Sprints.
Regarding the “Done” status, I’ve created three columns:
Done (RC)
Stable Released
Delete
When tasks are moved to any of these columns and the Sprint is completed, Jira still reports the following message:
“This sprint contains 0 completed work items and 1953 open work items.”
Additionally, these tasks remain visible when a new Sprint starts, instead of being marked as completed and cleared out.
This behavior makes the board look quite messy and confusing for users.
Request
Could you please advise on the possible cause or suggest a way to fix this issue?
Thank you very much.