Challenge:
Looking for a way to show number of new issues vs done issues over a rolling 24hrs
Goal:
Simple method to gauge early risk when counts start going up instead of down.
Sometimes the focus is so tight on getting planned work done, stakeholders lose sight of the growth of new issues (bugs or added stories). Progress may appear to slow when we are opening more issues than we are closing.
Question:
What JQL query might help display status changes for the last 24hrs limited to issues opened (created) vs issues done (closed, etc)?
Is that possible?
Currently Using Separately :
NEW ISSUE JQL
project = FS AND issuetype IN (Bug, Story, Task) AND created >= -24h ORDER BY status ASC, Key ASC
DONE ISSUES JQL:
issuetype in (Bug, Story, Task) AND status in ("UAT-DONE", "Closed", "UAT Ready") AND status CHANGED TO ("UAT-DONE", "Closed", "UAT Ready") AFTER -24h ORDER BY status ASC, updated ASC