Hi guys, can you help me a little with the logic or structure of an automation rule that meets the following requirements:
- When creating a story, 7 subtasks must be created.
- Each of these subtasks must have the start date (custom field) and due date (native field) fields among their fields. (This is already done.)
- The start date field must be a non-editable field.
- The due date of subtask 1 must be the start date of subtask 2, and so on until the last subtask.
Example: If the due date of subtask 1 is 01/08/25, that same date must be the start date of subtask 2. If subtask 2 has a due date of 07/08/25, that date must be the start date of subtask 3, and so on in that order.
- If the customer changes the due date of a subtask, the start date of the next subtask is updated.
Example: Taking the previous example as a reference, where the due date for subtask 1 is 01/08/25 and the start date for subtask 2 takes the same value, if the client decides to change and extend the due date for subtask 1 by one week to 08/08/25, the start date for subtask 2 would be updated to this new value.