Dear Team,
I need help configuring an automation rule in Jira. Below is the requirement.
We have the following fields.
"Delay in minutes" --- Number type
"FE Date/time" --- Date/time picker
"PS Date/time" --- Date/time picker
Here is the user case:
1. when a value is entered in the "Delay in minutes" (eg: 60 minutes)
2. The rule should look at the issue linked by "has to be done before"
3. It should retrieve the "FE Date/time" from that linked issue.
4. Then Calculate and update PS = FE (From linked issue) + Delay (from current issue)
5. Finally, it should update the PS field of the current issue with the result.
Example:
Task PS FE Delay in minutes
Task 1 PS 1 FE 1 Delay 1 = empty
Task 2 PS 2 FE 2 Delay 2 = 60 minutes
Link Type: Task 2 linked to Task 1 using "has to be done after"
Desired Logic:
If delay2 = 60 minutes, and task 2 is linked to Task 1, then PS2 = FE1 + Delay 2
Please help me configure this automation correctly.
Warm regards
MR Shaik