Hi all,
I am having trouble viewing the start and end date of tasks (some tasks can be shown properly, e.g. CMS-28 as shown below) in timeline, can anyone help me on this?
Thank you in advance.
Harry
Hi @Harry Chung
It looks like your CMS-28 lines up with your CMS Sprint 3, do you have your view set up to show dates by sprint?
In your timeline settings, under Timeline configuration > Timeline,is it currently set to "Scheduled by start and due date" or "Scheduled by sprint dates"?
Hi @Harry Chung welcome to the Atlassian Community Forums!
In the lower-right corner of your Timeline view you can change the period: Today | Weeks | Months | Quarters.
If the bar is not visible, click the < button.
Hi @Dave Mathijs ,
From my screenshot you can see that the start and end date of task CMS-41 is Jul 21-25, But the bar is not visible in July.
It was set to show dates by sprint, and my problem is fixed by changing to show by start and due dates, thanks a lot!
It was set to show by sprint date, and my problem is fixed by changing to show by start and due dates, thanks a lot!