We use Jira SLA feature for the Time to Resolution targets in the JSM projects. We are wondering whether the following SLA adjustment logic is feasible to implement in Jira? At the same time, we're curious how other companies addressed similar concern.
Problem:
It happens that a priority of an incident is elevated. What is currently happening in such situations, the SLAs (both time to resolution and time to first response) often immediately breach, due to shorter time associated with higher priority (usually 8h → 4h TtR and 30m → 15m TtFr).
It doesn't leave any space for engineers to react and meet targets.
Reporting on such cases is very problematic.
Our vision on how to address such scenario:
Logic to apply when issue priority changes:
• If the remaining SLA time is less than or equal to the target associated with the new priority → continue the current SLA without changes.
• If the remaining SLA time is greater than the new priority's SLA target → stop the current SLA and start a new one with the updated, shorter target.
Questions:
Can this be achieved with native Jira functionality? Does best practises/ITSM/experince provides other solutions for such cases?
Thanks in advance or any help:)