I can do things like A must be finished before B can start.
I'd like to do more complex such as:
* A and B need to finish together
* D can start # days after C starts or D can start # days after C ends
Hello @gordon.varney
Currently Jira Cloud Plans support just one dependency type; A must finish before B can start.
https://support.atlassian.com/jira-software-cloud/docs/what-are-dependencies-in-advanced-roadmaps/
For more complex dependency options you would need to consider a third party app that can integrate with Jira, from the Atlassian Marketplace. There are several such apps available, but I have not worked with them so I don't have a specific recommendation.
Trudy, many thanks, and yes I saw afterwards I basically posted the same question twice. Grrr.
Going to look at your code again and play with those notions.
Many thanks.