If I move a story to another epic in Portfolio Cloud, the epic in Agile isn't updated?
How do I get it to sync?
Did you update JIRA afterwards? Plan > Update Linked Issues
https://confluence.atlassian.com/display/JIRAPortfolioServer/Importing%2C+Syncing+and+Updating#Importing,SyncingandUpdating-DochangesinJIRAPortfoliodirectlyimpactmyJIRAproject?
Same question here. And yes - we did "Plan -> Apply updates to project/s". Issue doesn't moves from one epic to the other.
Same here, I've reverted to updating the epic link manually and re-importing into Portfolio. Will let you know if it works out. Did you come up with a solution? Is there a bug or ticket logged for this?
Same here. Has anyone tried removing the old epic link manually?