I have a Workload Pie chart, with a filter that looks at all standard level issues.
We do all our original estimates on the subtasks of the standard issues. This way, the actual original estimate of the standard issue is zero, but the sum of original estimates is the sum of the original estimates from its subtasks.
When setting the pie chart to show original estimate by issue type, using the filter for only standard issues, the sum of the subtasks original estimates is not aggregated to provide an idea of the estimates on these standard issues.
The pie chart will be blank.
I need a way to display the sum of original estimates by issue type, to determine that I am planning to my capacity.